Overview
TopTeam provides the flexibility to move a requirement or requirements from one Requirements Document to another.
Who should read this?
- TopTeam Users
The following Requirements Document illustrates the method of moving requirements from one Requirements Document to another
Step 1. Select the requirement(s) and click the More drop-down menu
Select Parent Requirement window opens
Here, you can select the destination Project and Record Type to which you want to move the requirements.
Step 2. Select a Project and Record Type
NOTE: If you select a Requirements Type (Record Type) that is different from the Requirements Type of the selected requirements, the requirements will then be converted to the selected Requirements Type.
Step 3. Select Requirements Document to which you want to move the Requirements
Requirements are moved to the selected destination.
Step 4. View the requirements you have moved
Step 5. Select the destination Requirements Document
Step 6. You will find the requirements have been moved
Revised: September 24th, 2016