Overview
In TopTeam, you can revert a project to a baseline by creating a branch from baseline, and deleting the existing project.
This article explains how to revert a project to a baseline.
Who should read this?
- TopTeam Users
- Project Admins
Step 1. Create a branch from a project baseline
Existing Project Baseline
NOTE: Baseline must be a Complete Baseline.
While creating a branch, ensure that you are adding all record types and issue types (tracking items).
Refer to the following process demonstration on creating a branch from a baseline:
Step 2. After branch has been created from a baseline, delete the existing project
Step 3. Confirm delete
Note: You can also revert a project to a baseline, by creating a new project from baseline.
Revised: September 11th, 2019